Welcome to the AlpTransit Gotthard LTD

Communiqué of 02.02.2010

Status of Work on the Gotthard and Ceneri

Gotthard Nord

As of February 1, 2010, of the total of 151.84 km of tunnels, galleries and passages of the Gotthard Base Tunnel, 142.48 km, or 93.84 %, had been excavated. The total amount driven in January 2009 was 664 m.

Of the total of...

more
Communiqué of 25.01.2010

Preparatory work for railway infrastructure installations

Today, Monday, January 25, 2010, in the Camorino area between Giubiasco and Cadenazzo, modifications began to the railway infrastructure installations on the existing line of Swiss Federal Railways. The modifications are first preparatory measures...

more
Communiqué of 10.12.2009

Structurally complete tunnels of the Amsteg section handed over

At Amsteg the constructors of the Gotthard Base Tunnel have reached a further milestone. Almost eight years after the contract was signed, the Gotthard Base Tunnel North (AGN) consortium has handed over the structurally complete tunnels of the...

more

Ceneri - State of excavation

Watch the tunnellers at work ? the new documentary film "AlpTransit Gotthard 2008" makes it possible. The milestones and progress achieved in 2008 on the construction sites of the Gotthard and Ceneri tunnels are available on DVD.

continue