Status of Work on the Gotthard and Ceneri

01.09.2010

Gotthard Base Tunnel: Erstfeld

Gotthard Base Tunnel: Erstfeld

As of September 1, 2010, of the total of 151.84 km of tunnels, galleries and passages of the Gotthard Base Tunnel, 147.98 km, or 97.5%, had been excavated. The total amount driven in August 2010 was 608 m.

Of the total of 39.78 km of the Ceneri Base Tunnel, at the end of August 2010, 9102m, or 22.9%, had been excavated.

Noch 478 m bis zum Weltrekord

Ceneri - State of excavation

Watch the tunnellers at work - the new documentary film "AlpTransit Gotthard 2009" makes it possible. The milestones and progress achieved in 2009 on the construction sites of the Gotthard and Ceneri tunnels are available on DVD.