Status of Work on the Gotthard and Ceneri
02.02.2010
As of February 1, 2010, of the total of 151.84 km of tunnels, galleries and passages of the Gotthard Base Tunnel, 142.48 km, or 93.84 %, had been excavated. The total amount driven in January 2009 was 664 m.
Of the total of 40.19 km of the Ceneri Base Tunnel, at the end of January 2010, 7,637 m, or 19%, had been excavated.