Milestone under the Gotthard: Today, Monday, December 16, 2013, Swiss Federal Councillor Doris Leuthard officially opened pilot operation in the west tube of the Gotthard Base Tunnel. For the first time, a train travelled over the approximately 13-kilometres-long pilot section from Bodio to Faido at a speed of 160 km/h. Pilot operation will provide important information in preparation for opening the Gotthard Base Tunnel to scheduled train services in December 2016. Until the official...More

The Swiss Federal Administrative Court has ordered the awards made by AlpTransit Gotthard Ltd. of the railway system lots "Railway Track & Logistics" and "Railway Systems and Overall Coordination" for the Ceneri Base Tunnel to be postponed pending consideration of the two appeals. Should the awards not become legally effective by the end of this year, effects on the scheduled date for opening of the Ceneri Base Tunnel in 2019 cannot be ruled out. On August 12, 2013,...More

Some of the drainage pipes installed in the Gotthard Base Tunnel display reduced durability. This is the conclusion of SKZ Kunststoff Zentrum Würzburg, which was commissioned by AlpTransit Gotthard Ltd. to test the pipe material. However, based on this knowledge and the test results, the replacement of already installed drainage pipes is not an issue for discussion. As things stand today, there is nothing to prevent commissioning of the Gotthard Base Tunnel at the end of 2016. According to...More

Gotthard premiere: today, August 30, 2013, the first trip was made through the entire Gotthard Base Tunnel from Bodio to Erstfeld. Together with the main contractors involved in constructing the tunnel as well as project planners and the railway systems consortium, AlpTransit Gotthard Ltd. as tunnel constructor took media representatives on a trip through the world's longest tunnel. They travelled the 57-kilometres-long route by train, in buses and on foot. Until the tunnel is ready for...More

Since the start of construction work on the Gotthard, the world's longest tunnel has attracted tens of thousands of visitors to the NRLA construction sites and the information centres at Erstfeld, Sedrun and Pollegio. On August 23, 2013, AlpTransit Gotthard Ltd. could welcome the one millionth visitor at the Erstfeld information centre. The visitor belonged to a group from Switzerland which visited the Erstfeld information centre and the construction site at Amsteg. Renzo Simoni, Chief...More

At its meeting held on August 12, 2013, the Board of Directors of AlpTransit Gotthard Ltd. awarded the contract for the railway infrastructure systems of the Ceneri Base Tunnel. The "Railway Infrastructure Systems and Overall Coordination" lot is awarded to the CPC consortium. The "Track and Logistics" lot goes to the Mons Ceneris consortium. Installation of the railway infrastructure systems will begin at the end of 2016. The Ceneri Base Tunnel is scheduled to open for...More

04. April 2013

Switzerland's biggest-ever construction project is making good progress. This is evidenced by the latest annual film from AlpTransit Gotthard Ltd., which in around 30 minutes illustrates the most important work steps of 2012. The film was presented to the public at a premiere in Erstfeld on April 2nd, 2013. The film documents the progress of construction in 2012. The year is characterised by the transition from tunnel construction to installation of the railway infrastructure...More

Work on the Gotthard and Ceneri base tunnels is on course. Inside the Gotthard Base Tunnel, in both tunnel tubes between Erstfeld and Sedrun, the ballastless railway track has been laid. In total, more than 40 percent of the railway systems have been installed. Pilot operation between the south portal at Bodio and Faido will start on schedule in December 2013 - a further important milestone towards the world's longest railway tunnel becoming operational in 2016. In the Ceneri Base Tunnel,...More

In the last few months, the exhibition in the AlpTransit Gotthard South Information Centre at Pollegio has been renewed and updated. The exhibition now also shows installation of the railway systems. With audio-visual media and exhibits, the complex work on the NRLA axis under the Gotthard is comprehensibly explained. There is also a new section devoted to construction of the Ceneri Base Tunnel. Guided tours of the construction sites can still be booked at the Information Centre. The focus...More